I-Move Weekend Report: Closures Planned at I-71/I-265

Milling and paving work will begin at 8 p.m. Friday, June 26

Contractors for the Kentucky Transportation Cabinet’s I-Move Kentucky Project are continuing significant roadway improvement work this weekend to lessen impacts on weekday travelers.

Crews will perform milling and paving work on Interstate 71 southbound at the interchange with the Gene Snyder Freeway (I-265). Work in this area will start around 8 p.m. Friday and continue through 6 a.m. Monday. Drivers should be cautious when traveling in this area. Signage and flaggers will be in place to alert drivers of lane closures and construction zones.

  • One lane of I-71 southbound will be closed.
  • Three ramps at the interchange will be closed overnight at various times during the weekend:
    • I-71 southbound to I-265 southbound
    • I-71 southbound to I-265 northbound
    • I-265 northbound to I-71 southbound
  • Starting tonight at 8 p.m.
  • Ending Monday, June 29 at 6 a.m.
  • Located between mile point 8.7 and mile point 9.8 of I-71

Work schedules may be adjusted due to inclement weather or other unforeseen delays occur.

About I-Move Kentucky

The I-Move Kentucky project includes improvements to four, major sections of I-265, I-71 and I-64 through a heavily traveled corridor in Jefferson and Oldham counties. Work on the I-Move project is scheduled to be completed by the end of 2023. Stay informed through the following channels:

Website – www.I-MoveKY.com
Facebook – facebook.com/IMoveKY/
Twitter – twitter.com/IMoveKY
Email alerts/newsletters – Signup at www.I-MoveKY.com
Mobile alerts – Text “IMOVEKY” to 50597

Week Ahead: Roadway Work Continues on I-71 and I-265

Lane and ramp closures expected this week on I-Move KY project

The Kentucky Transportation Cabinet advises motorists of upcoming traffic impacts this week as construction continues in several areas across the I-Move Kentucky project. This work will involve overnight and weekend lane closures in some areas of the project.

Drivers should be cautious when traveling in these areas. Signage and flaggers will be in place to alert drivers of lane closures and construction zones. Work schedules may be adjusted due to inclement weather or other unforeseen delays.

Gene Snyder Freeway, between Interstate 64 and Taylorsville Road – A construction crew will continue asphalt and roadway work in preparation for the eventual widening of Gene Snyder Freeway (I-265). Crews also are working on relocating utilities in the median area.

  • One lane of I-265 in either direction may be closed overnight.
  • Work is planned Tuesday through Thursday.
  • Lane closures may be in place from 8 p.m. to 6 a.m.
  • Located between mile point 23 and mile point 25 of I-265.

I-71/I-265 interchange – Milling and paving work continues this weekend on lanes of I-71.

  • One lane of I-71 southbound will be closed.
  • Three ramps at the interchange will be closed overnight at various times during the weekend:
    • I-71 southbound to I-265 southbound
    • I-71 southbound to I-265 northbound
    • I-265 northbound to I-71 southbound
  • Starting Friday, June 26 at 8 p.m.
  • Ending Monday, June 29 at 6 a.m.
  • Located between mile point 8.7 and mile point 9.8 of I-71

I-265 bridge over I-71 – Crews will begin working in the area for the eventual widening of the bridge.

  • Northbound traffic on I-265 will be shifted slightly, and temporary barriers will be installed.
  • Traffic on I-71 may be affected for short periods overnight as crews deconstruct portions of the bridge to widen it.
  • Stoppages on I-71 would occur between 8 p.m. and 6 a.m.
  • Located at mile point 35 of I-265 northbound.

Brownsboro Road (KY 1694) bridge over I-71 – Crews continue construction of a retaining wall in preparation to replace the bridge over I-71. A water transmission line is also being relocated in the area in preparation of bridge construction.

  • Work started in mid-May
  • Short, periodic stoppages of traffic on KY 1694 (Brownsboro Road) may be necessary

I-265 bridges over La Grange Road – Maintenance and concrete patching work continues as part of improvements to I-265.

  • Project started this month
  • No traffic impacts are expected

 I-265 bridges over Westport Road – Maintenance and concrete patching work continues as part of improvements to I-265.

  • Project started in early May
  • No traffic impacts are expected

About I-Move Kentucky

The I-Move Kentucky project includes improvements to four, major sections of I-265, I-71 and I-64 through a heavily traveled corridor in Jefferson and Oldham counties. Work on the I-Move project is scheduled to be completed by the end of 2023. Stay informed through the following channels:

Website – www.I-MoveKY.com
Facebook – facebook.com/IMoveKY/
Twitter – twitter.com/IMoveKY
Email alerts/newsletters – Signup at https://mailchi.mp/466096afc3a4/i-moveky
Mobile alerts – Text “IMOVEKY” to 50597

I-Move Weekend Report: Closures Planned at I-71/I-265

Milling and paving work will begin at 8 p.m. Friday, June 19

Contractors for the Kentucky Transportation Cabinet’s I-Move Kentucky Project are continuing significant roadway improvement work this weekend to lessen impacts on weekday travelers.

Contractors for the I-Move Kentucky project will be working this weekend on Interstate 71.

Crews will perform milling and paving work on Interstate 71 northbound at the interchange with the Gene Snyder Freeway (I-265). Work in this area will start around 8 p.m. Friday and continue through 6 a.m. Monday. Drivers should be cautious when traveling in this area. Signage and flaggers will be in place to alert drivers of lane closures and construction zones.

  • Ramp from I-71northbound to I-265 northbound will be closed overnight Friday until Saturday morning.
  • One lane of I-71 northbound will be closed throughout the weekend.
  • Work will occur between mile point 8.7 and mile point 9.8 of I-71.
  • Work on I-71 southbound is tentatively planned for the weekend of June 26-29.

Work schedules may be adjusted due to inclement weather or other unforeseen delays occur.

About I-Move Kentucky

The I-Move Kentucky project includes improvements to four, major sections of I-265, I-71 and I-64 through a heavily traveled corridor in Jefferson and Oldham counties. Work on the I-Move project is scheduled to be completed by the end of 2023. Stay informed through the following channels:

Website – www.I-MoveKY.com
Facebook – facebook.com/IMoveKY/
Twitter – twitter.com/IMoveKY
Email alerts/newsletters – Signup at www.I-MoveKY.com
Mobile alerts – Text “IMOVEKY” to 50597

I-Move Kentucky Plans Weekend Lane Closures on I-71

Milling and paving work will begin at 8 p.m. Friday, June 19 

The Kentucky Transportation Cabinet advises motorists of upcoming traffic impacts this week as construction work continues in several areas across the I-Move Kentucky project. This work will involve overnight and weekend lane closures as well as temporary stoppages of traffic in some areas.

A major component of the I-Move Kentucky project starts this week with roadway work on Interstate 71 at the interchange with the Gene Snyder Freeway (I-265). Milling and paving work is planned over the next two weekends.

  • One lane of I-71 northbound will be closed
  • Starting Friday, June 19 at 8 p.m.
  • Ending Monday, June 22 at 6 a.m.
  • Located between mile point 8.7 and mile point 9.8 of I-71
  • Work on southbound I-71 is tentatively planned for weekend of June 26-29

Other construction

Construction and engineering work also is underway on the I-Move Kentucky project in the following project areas. Drivers should be cautious when traveling in these areas. Signage and flaggers will be in place to alert drivers of lane closures and construction zones.

I-64/I-265 interchange – A crew will be performing geotechnical drilling in median areas to prepare for construction.

  • Left lane of I-64 westbound will be closed Monday, June 15
  • Right lane of I-265 northbound will be closed Tuesday, June 16
  • Work will occur overnight, from 8 p.m. to 6 a.m.

Gene Snyder Freeway, between Interstate 64 ramps and Taylorsville Road – A construction crew will continue asphalt and roadway work in preparation for the eventual widening of I-265. Crews also will remove existing cable barriers and begin underground utility work.

  • Located between mile point 23 and mile point 25 of I-265
  • No traffic impacts are expected

Brownsboro Road (KY 1694) bridge over I-71 – Crews continue construction of a retaining wall in preparation to replace the bridge over I-71. A water transmission line is also being relocated in the area in preparation of bridge construction.

  • Work started in mid-May
  • Short, periodic stoppages of traffic on KY 1694 (Brownsboro Road) may be necessary

I-265 bridges over La Grange Road – Maintenance and concrete patching work continues as part of improvements to I-265.

  • Project started this month
  • No traffic impacts are expected

I-265 bridges over Westport Road – Maintenance and concrete patching work continues as part of improvements to I-265.

  • Project started in early May
  • No traffic impacts are expected

About I-Move Kentucky

The I-Move Kentucky project includes improvements to four, major sections of I-265, I-71 and I-64 through a heavily traveled corridor in Jefferson and Oldham counties. Work on the I-Move project is scheduled to be completed by the end of 2023. Stay informed through the following channels:

Website www.I-MoveKY.com
Facebook – facebook.com/IMoveKY/
Twitter – twitter.com/IMoveKY
Email alerts/newsletters – Signup at www.I-MoveKY.com
Mobile alerts – Text “IMOVEKY” to 50597

Ramp Closure Planned Overnight Friday

Paving crews will close I-64 eastbound ramp to southbound I-265

KYTC will close the ramp from I-64 eastbound to I-265 southbound overnight for milling work.

Construction crews for the Kentucky Transportation Cabinet’s I-Move Kentucky project will close the ramp from I-64 eastbound to I-265 southbound overnight. The closure of the ramp will allow crews to mill the existing roadway and replace the asphalt in preparation for the eventual widening of the Gene Snyder Freeway (I-265).

Work on the ramp at Exit 19A will begin Friday night and continue through Saturday morning. The ramp will be closed from 8 p.m. to 6 a.m., and a detour will be in place. Access will be maintained for emergency vehicles.

Signage and flaggers will be in place to alert drivers of the ramp closure. Detour signs will reroute traffic through the other ramps of the interchange, using I-265 northbound and I-64 westbound to reach another ramp for I-265 southbound ramp.

I-265 lane closures continuing

Potential lane closures also remain in effect though a stretch of I-265, just south of the interchange.

Milling and asphalt work is underway on I-265, between the I-64 ramps and the Taylorsville Road interchange. The work zone runs from mile point 23 to mile point 25 of I-265. Nightly lane closures of one lane in either direction will be in place between 8 p.m. and 6 a.m.

The planned closures are tentative and may be affected by weather.

*Note: the originally planned closure for Thursday, June 4 was moved to Friday, June 5 due to inclement weather.