Week Ahead: Construction Work Continues with Minimal Traffic Impacts

Excavation work continues along I-71, asphalt installation at I-71/I-265 interchange planned later this week

The Kentucky Transportation Cabinet continues to make progress on the I-Move Kentucky project as crews work in several areas of I-71 and I-265. No major impacts to traffic are planned this week.

Drivers should be cautious when traveling through active construction areas. Signage and flaggers will be in place to alert drivers of lane closures and construction zones. Work schedules may be adjusted due to inclement weather or other unforeseen delays.

Current I-Move Kentucky Work Areas

I-71 northbound at Moser Farm Road – Blasting work on I-71 northbound and southbound at Moser Farm Road is under way and will continue daily this week. Excavation work is needed to eventually widen this area of the I-71 corridor to a total of six lanes. Rolling lane closures and short-term road closures will take place on both northbound and southbound lanes daily, including some weekends, between noon and 3 p.m. while blasting is completed near mile point 11.8 of I-71 northbound.

I-71/I-265 interchange – Crews recently completed work for a soil nail wall and cement stabilization with paving planned to start this week. This work along the southbound lanes of I-71 and the widening of the corridor to add a collector-distributor lane will improve safety for vehicles entering and exiting I-71 southbound. No traffic impacts are expected as work continues at mile point 9.1.

I-71 southbound between Brownsboro Road bridge and I-265 bridge – Preparation work in this area is ongoing to allow for widening of the corridor and construction of a new Brownsboro Road (KY 1694) bridge over I-71. This work zone is located between mile point 10.3 and mile point 9.1 of I-71 southbound. No traffic impacts are expected this week.

I-71 southbound between Highway 329 and the rest area – Crews continue to work to extend a culvert that will allow for the widening of I-71. No traffic impacts are expected as work continues between mile point 14.5 and mile point 13.5 of I-71 southbound.

I-265 between Taylorsville Road and I-64 – Crews are continuing to perform drainage and lane widening work in the median between northbound and southbound lanes of I-265 between Taylorsville Road and I-64. No traffic impacts are expected as work continues between mile point 25.4 and mile point 23.1.