A major traffic switch for the existing I-64 East to I-265 North ramp is scheduled for Sunday, June 9. This work is part of the I-Move Kentucky project. 

The ramp from I-64 West to I-265 North will be closed on Sunday to complete tie-ins related to the new ramp opening. The ramp from I-64 West to I-265 North (Exit 19B) will open again at approximately 6 p.m., Sunday. 

Beginning at 6 a.m. Sunday, I-64 East will be down to one lane beginning at Blankenbaker Parkway to allow crews to relocate existing signs and remove old signage. When complete, I-64 East will reopen to two lanes at approximately noon. 

The new ramp from I-64 East to I-265 North (Exit 19B) will open at the same time the Exit 19B cloverleaf will permanently be closed. Work should be completed by 6 p.m. on Sunday.  

Exits 19A and 19B on I-64 will have brief closures to traffic to complete proper lane assignment and striping for the new ramp. These closures will be in place from 6 a.m. to 6 p.m. on Sunday. 

Signage will be in place to alert drivers of the new I-265 exit pattern starting at Hurstbourne Lane to Blankenbaker Parkway. A message board will also be up to alert drivers that Exit 19B will be closed starting Sunday.  

Work may be adjusted due to weather or other unforeseen events. 