I-Move Week Ahead: Work near I-64/I-265 interchange requires lane closure

Traffic on I-265 will be impacted Monday and Tuesday nights

The Kentucky Transportation Cabinet continues to make progress on the I-Move Kentucky project as crews work in several areas of I-71 and I-265. Milling and paving work will impact traffic this week.

Traffic on I-265 will be reduced to one lane on Monday and Tuesday evenings between 8 p.m. and 6 a.m. between Shelbyville Road at mile point 26.8 and the I-64 interchange at mile point 25.4 for milling and paving operations. Lanes will be shifted for ongoing work to improve safety and mobility by rebuilding the I-64/I-265 interchange.

Looking ahead to the weekend, paving and milling operations on a two-mile stretch of I-71 northbound will require traffic to be reduced to one lane from Saturday at 12 a.m. to Monday at 6 a.m. Lane closures will start north of Chamberlain Lane near mile marker 9.8 on I-71 northbound and end near Moser Farm Road at mile marker 11.8.

Work schedules may be adjusted due to weather or other unforeseen delays. Drivers should be cautious when traveling through active construction areas. Signage and flaggers will be in place to alert drivers of lane closures and construction zones.

Other I-Move Kentucky Work Areas

I-64/I-265 interchange – Work to rebuild the interchange listed above will impact traffic on I-265 this weekend between Shelbyville Road at mile point 26.8 and the I-64 interchange at mile point 25.4.

I-71 northbound to Moser Farm Road – Paving operations listed above will impact traffic this weekend. Also, blasting work on I-71 northbound and southbound at Moser Farm Road is under way and continues daily. Excavation work is needed to eventually widen this area of the I-71 corridor to a total of six lanes. Rolling lane closures and short-term road closures will take place on both northbound and southbound lanes daily, including some weekends, between noon and 3 p.m. while blasting is completed near mile point 11.8 of I-71 northbound.

I-71/I-265 interchange – Work on new bridges, access ramps, along I-71 and the widening of the corridor to add a collector-distributor lane will improve safety for vehicles entering and exiting I-71 at mile point 9.1. No traffic impacts are planned this weekend

I-71 southbound between Brownsboro Road bridge and I-265 bridge – Preparation work in this area is ongoing to allow for widening of the corridor and construction of a new Brownsboro Road (KY 1694) bridge over I-71. This work zone is located between mile point 10.3 and mile point 9.1 of I-71 southbound. No traffic impacts are expected this week.

I-71 southbound between Highway 329 and the rest area – Crews continue to work to extend a culvert that will allow for the widening of I-71. No traffic impacts are expected as work continues between mile point 14.5 and mile point 13.5 of I-71 southbound.

I-265 between Taylorsville Road and I-64 – Interior lanes of I-265 between Taylorsville Road and I-64 were recently paved. No traffic impacts are anticipated as crews perform this work and continue drainage and lane widening work in the median between mile point 25.4 and mile point 23.1.

I-Move Weekend Report: Paving on I-71 requires lane closure this weekend

Traffic on I-71 northbound to the east of the I-71/I-265 interchange will be impacted

The Kentucky Transportation Cabinet continues to make progress on the I-Move Kentucky project as crews work in several areas of I-71 and I-265.

Paving operations this weekend on a two-mile stretch of I-71 northbound will require traffic to be reduced to one lane from Friday at 8 p.m. to Monday at 6 a.m. Lane closures will start north of Chamberlain Lane near mile marker 9.8 on I-71 northbound and end near Moser Farm Road at mile marker 11.8.

Work schedules may be adjusted due to weather or other unforeseen delays. Drivers should be cautious when traveling through active construction areas. Signage and flaggers will be in place to alert drivers of lane closures and construction zones.

Other I-Move Kentucky Work Areas

I-71 northbound at Moser Farm Road – Paving operations listed above will impact traffic this weekend. Also, blasting work on I-71 northbound and southbound at Moser Farm Road is under way and continues daily. Excavation work is needed to eventually widen this area of the I-71 corridor to a total of six lanes. Rolling lane closures and short-term road closures will take place on both northbound and southbound lanes daily, including some weekends, between noon and 3 p.m. while blasting is completed near mile point 11.8 of I-71 northbound.

I-71/I-265 interchange – Work on new bridges, access ramps, along I-71 and the widening of the corridor to add a collector-distributor lane will improve safety for vehicles entering and exiting I-71 at mile point 9.1. No traffic impacts are planned this weekend

I-71 southbound between Brownsboro Road bridge and I-265 bridge – Preparation work in this area is ongoing to allow for widening of the corridor and construction of a new Brownsboro Road (KY 1694) bridge over I-71. This work zone is located between mile point 10.3 and mile point 9.1 of I-71 southbound. No traffic impacts are expected this week.

I-71 southbound between Highway 329 and the rest area – Crews continue to work to extend a culvert that will allow for the widening of I-71. No traffic impacts are expected as work continues between mile point 14.5 and mile point 13.5 of I-71 southbound.

I-265 between Taylorsville Road and I-64 – Paving on interior lanes of I-265 between Taylorsville Road and I-64 will begin Wednesday night. No traffic impacts are anticipated as crews perform this work and continue drainage and lane widening work in the median between mile point 25.4 and mile point 23.1.

I-Move Week Ahead: Lane closures planned for bridge work Monday and Tuesday nights

Traffic near I-71/I-265 interchange will be impacted

 The Kentucky Transportation Cabinet continues to make progress on the I-Move Kentucky project as crews work in several areas of I-71 and I-265. Construction work at the I-71/I-265 interchange will impact traffic this week.

Deck work on the I-265 bridge over I-71 will require traffic on I-71 to be reduced to one lane Monday and Tuesday overnight from 8 p.m. until 6 a.m. Lane closures will start near mile marker 8.7 on I-71 northbound and near mile marker 9.8 on I-71 southbound as they approach the I-265 interchange.

Work schedules may be adjusted due to weather or other unforeseen delays. Drivers should be cautious when traveling through active construction areas. Signage and flaggers will be in place to alert drivers of lane closures and construction zones.

Other I-Move Kentucky Work Areas

I-71/I-265 interchange – Traffic impacts this week listed above include lane closures on I-71 near the interchange. Work on new bridges, access ramps, along I-71 and the widening of the corridor to add a collector-distributor lane will improve safety for vehicles entering and exiting I-71 at mile point 9.1.

I-71 northbound at Moser Farm Road – Blasting work on I-71 northbound and southbound at Moser Farm Road is under way and continues daily. Excavation work is needed to eventually widen this area of the I-71 corridor to a total of six lanes. Rolling lane closures and short-term road closures will take place on both northbound and southbound lanes daily, including some weekends, between noon and 3 p.m. while blasting is completed near mile point 11.8 of I-71 northbound.

I-71 southbound between Brownsboro Road bridge and I-265 bridge – Preparation work in this area is ongoing to allow for widening of the corridor and construction of a new Brownsboro Road (KY 1694) bridge over I-71. This work zone is located between mile point 10.3 and mile point 9.1 of I-71 southbound. No traffic impacts are expected this week.

I-71 southbound between Highway 329 and the rest area – Crews continue to work to extend a culvert that will allow for the widening of I-71. No traffic impacts are expected as work continues between mile point 14.5 and mile point 13.5 of I-71 southbound.

I-265 between Taylorsville Road and I-64 – Paving on interior lanes of I-265 between Taylorsville Road and I-64 will begin Wednesday night. No traffic impacts are anticipated as crews perform this work and continue drainage and lane widening work in the median between mile point 25.4 and mile point 23.1.

I-Move Weekend Report: Lane closures planned for paving and construction work this weekend

Traffic on I-71 and at the I-71/I-265 interchange will be impacted

 The Kentucky Transportation Cabinet continues to make progress on the I-Move Kentucky project as crews work in several areas of I-71 and I-265. Construction work at the I-71/I-265 interchange and paving operations on I-71 will impact traffic this weekend. Work schedules may be adjusted due to weather or other unforeseen delays.

Milling and paving work on I-71 southbound and deck work on two bridges over I-71, the I-265 bridge and Brownsboro Road bridge, will require traffic on I-71 to be reduced to one lane throughout the weekend from Friday at 8 p.m. until 6 a.m. Monday. Lane closures will take place on I-71 northbound and southbound starting before the I-265 interchange at mile marker 8.7 and continuing to near the Oldham County line at mile marker 11.

Drivers should be cautious when traveling through active construction areas. Signage and flaggers will be in place to alert drivers of lane closures and construction zones.

Other I-Move Kentucky Work Areas

I-71/I-265 interchange – Traffic impacts this week listed above include lane closures on I-71 near the interchange. Work on new bridges, access ramps, along I-71 and the widening of the corridor to add a collector-distributor lane will improve safety for vehicles entering and exiting I-71 at mile point 9.1.

I-71 northbound at Moser Farm Road – Blasting work on I-71 northbound and southbound at Moser Farm Road is under way and continues daily. Excavation work is needed to eventually widen this area of the I-71 corridor to a total of six lanes. Rolling lane closures and short-term road closures will take place on both northbound and southbound lanes daily, including some weekends, between noon and 3 p.m. while blasting is completed near mile point 11.8 of I-71 northbound.

I-71 southbound between Brownsboro Road bridge and I-265 bridge – Preparation work in this area is ongoing to allow for widening of the corridor and construction of a new Brownsboro Road (KY 1694) bridge over I-71. This work zone is located between mile point 10.3 and mile point 9.1 of I-71 southbound. No traffic impacts are expected this week.

I-71 southbound between Highway 329 and the rest area – Crews continue to work to extend a culvert that will allow for the widening of I-71. No traffic impacts are expected as work continues between mile point 14.5 and mile point 13.5 of I-71 southbound.

I-265 between Taylorsville Road and I-64 – Paving on interior lanes of I-265 between Taylorsville Road and I-64 will begin Wednesday night. No traffic impacts are anticipated as crews perform this work and continue drainage and lane widening work in the median between mile point 25.4 and mile point 23.1.

I-Move Week Ahead: Ramp closure planned overnight Wednesday at I-71/I-265 interchange

Ramp from I-265 southbound to I-71 southbound closed from 8 p.m. to 6 a.m.

The Kentucky Transportation Cabinet continues to make progress on the I-Move Kentucky project as crews work in several areas of I-71 and I-265. Construction work at the I-71/I-265 interchange will impact traffic this Wednesday night.

The ramp from I-265 southbound to I-71 southbound will be closed Wednesday at 8 p.m. to Thursday at 6 a.m. to allow crews to shift a barrier wall and perform grading work.

Drivers should be cautious when traveling through active construction areas. Signage and flaggers will be in place to alert drivers of lane closures and construction zones. Work schedules may be adjusted due to inclement weather or other unforeseen delays.

Other I-Move Kentucky Work Areas

I-71/I-265 interchange – Traffic impacts this week listed above include a ramp closure overnight Wednesday at the interchange. Work on new bridges, access ramps, along I-71 and the widening of the corridor to add a collector-distributor lane will improve safety for vehicles entering and exiting I-71 at mile point 9.1.

I-71 northbound at Moser Farm Road – Blasting work on I-71 northbound and southbound at Moser Farm Road is under way and continues daily. Excavation work is needed to eventually widen this area of the I-71 corridor to a total of six lanes. Rolling lane closures and short-term road closures will take place on both northbound and southbound lanes daily, including some weekends, between noon and 3 p.m. while blasting is completed near mile point 11.8 of I-71 northbound.

I-71 southbound between Brownsboro Road bridge and I-265 bridge – Preparation work in this area is ongoing to allow for widening of the corridor and construction of a new Brownsboro Road (KY 1694) bridge over I-71. This work zone is located between mile point 10.3 and mile point 9.1 of I-71 southbound. No traffic impacts are expected this week.

I-71 southbound between Highway 329 and the rest area – Crews continue to work to extend a culvert that will allow for the widening of I-71. No traffic impacts are expected as work continues between mile point 14.5 and mile point 13.5 of I-71 southbound.

I-265 between Taylorsville Road and I-64 – Paving on interior lanes of I-265 between Taylorsville Road and I-64 will begin Wednesday night. No traffic impacts are anticipated as crews perform this work and continue drainage and lane widening work in the median between mile point 25.4 and mile point 23.1.

I-Move Weekend Report: Construction at I-71/I-265 and paving on I-71 require closures

Traffic will be impacted by road, lane and ramp closures this weekend 

The Kentucky Transportation Cabinet continues to make progress on the I-Move Kentucky project as crews work in several areas of I-71 and I-265. Construction work at the I-71/I-265 interchange and paving operations on I-71 northbound will impact traffic this weekend.

Several closures are planned starting Friday at 8 p.m. until 6 a.m. Saturday to accommodate work on a new bridge over I-71. Rolling road closures will be required across all lanes of I-71 in 15-minute intervals throughout the night as beams are set. The road closure on I-71 southbound will start near the rest area near mile point 12. The road closure on I-71 northbound will start at the I-264 (Watterson Expressway) interchange at mile point 5.1. Additionally, Brownsboro Road near I-71 will be reduced to one lane.

Throughout the weekend, paving operations on I-71 northbound will require lane closures between the I-71/I-265 interchange at mile point 9.1 and the Oldham County line near mile point 11. Overnight Friday the right lane will be closed as paving is under way. On Saturday afternoon, traffic will be shifted to newly paved lanes and the left lane will be closed and paved.

On Sunday afternoon until 6 a.m. Monday, the ramp from I-71 southbound to I-265 southbound will be closed to allow for crews to shift traffic.

Drivers should be cautious when traveling through active construction areas. Signage and flaggers will be in place to alert drivers of lane closures and construction zones. Work schedules may be adjusted due to inclement weather or other unforeseen delays.

Other I-Move Kentucky Work Areas

I-71/I-265 interchange – Traffic impacts this weekend listed above include road, lane and ramp closures at the interchange. Work on new bridges, access ramps, along I-71 and the widening of the corridor to add a collector-distributor lane will improve safety for vehicles entering and exiting I-71 at mile point 9.1.

I-71 northbound at Moser Farm Road – Blasting work on I-71 northbound and southbound at Moser Farm Road is under way and continues daily. Excavation work is needed to eventually widen this area of the I-71 corridor to a total of six lanes. Rolling lane closures and short-term road closures will take place on both northbound and southbound lanes daily, including some weekends, between noon and 3 p.m. while blasting is completed near mile point 11.8 of I-71 northbound.

I-71 southbound between Brownsboro Road bridge and I-265 bridge – Preparation work in this area is ongoing to allow for widening of the corridor and construction of a new Brownsboro Road (KY 1694) bridge over I-71. This work zone is located between mile point 10.3 and mile point 9.1 of I-71 southbound. No traffic impacts are expected this week.

I-71 southbound between Highway 329 and the rest area – Crews continue to work to extend a culvert that will allow for the widening of I-71. No traffic impacts are expected as work continues between mile point 14.5 and mile point 13.5 of I-71 southbound.

I-265 between Taylorsville Road and I-64 – Paving on interior lanes of I-265 between Taylorsville Road and I-64 will begin Wednesday night. No traffic impacts are anticipated as crews perform this work and continue drainage and lane widening work in the median between mile point 25.4 and mile point 23.1.