I-Move Week Ahead: Additional Lane and Ramp Closures on I-265, I-71 and I-64 Starting Tonight

Lane and ramp closures on I-265, I-71, and I-64 will be in place starting tonight, Wednesday, Oct. 2. New closures have been added in bold. This work is part of the I-Move Kentucky project. 

Wednesday, Oct. 2 

  • Beginning at 8 p.m., the La Grange Road ramp to I-265 northbound (Exit 30) will be closed for bridge maintenance work. This closure will be in place until Thursday at 6 a.m. 
  • At 8 p.m., the I-265 northbound to I-71 southbound (Exit 35B) ramp will be closed for bridge maintenance work. This closure will be in place until Thursday at 6 a.m.  
  • At 8 p.m., I-265 southbound from Brownsboro Road (Exit 34) headed towards the I-64/I-265 interchange will be reduced to one lane for roadside maintenance work. This closure will be in place until Thursday at 6 a.m. 
  • At 8 p.m., the beginning of the ramp from I-64 eastbound to I-265 southbound and I-265 northbound will be reduced to one lane for roadside sign installation work. This closure will be in place until Thursday at 6 a.m.  

Thursday, Oct. 3 

  • Beginning at 8 p.m., the I-265 northbound to I-71 southbound ramp (Exit 35B) will be closed for bridge maintenance work. This closure will be in place until Friday at 6 a.m. 

Friday, Oct. 4 

  • Beginning at 8 p.m., the ramp from I-64 westbound to Blankenbaker Parkway (Exit 17) will be closed for asphalt paving work. This closure will be in place until Monday at 6 a.m.  
  • At 8 p.m., I-265 northbound will be reduced to one lane south of I-64 to Shelbyville Road for permanent barrier wall installation work. This closure will be in place until Monday morning at 6 a.m.  

Work may be adjusted due to weather or other unforeseen events. Drivers should use caution when traveling through active work zones. 

I-Move Week Ahead: Lane and Ramp Closures on I-265, I-71 and I-64 Starting Tonight

Lane and ramp closures on I-265, I-71, and I-64 will be in place starting tonight, Monday, Sept. 30. This work is part of the I-Move Kentucky project. 

Monday, Sept. 30 

  • Beginning at 8 p.m., I-265 northbound will be reduced to one lane at I-71 for bridge maintenance work. This closure will be in place until Tuesday at 6 a.m. The same closure will be in place nightly starting Monday, Sept. 30 through Thursday, Oct. 3. 
  • At 8 p.m., I-265 southbound from Brownsboro Road to I-64 will be reduced to one lane for roadside maintenance work. This closure will be in place until Tuesday at 6 a.m.  

Tuesday, Oct. 1 

  • Beginning at 8 p.m., I-265 northbound from Brownsboro Road to I-64 will be reduced to one lane for roadside maintenance work. This closure will be in place until Wednesday at 6 a.m. 

Wednesday, Oct. 2 

  • Beginning at 8 p.m., the I-265 northbound to I-71 southbound (Exit 35B) ramp will be closed for bridge maintenance work. This closure will be in place until Thursday at 6 a.m.  
  • At 8 p.m., I-265 southbound from Brownsboro Road to I-64 will be reduced to one lane for roadside maintenance work. This closure will be in place until Thursday at 6 a.m. 
  • At 8 p.m., the beginning of the ramp from I-64 eastbound to I-265 southbound and I-265 northbound will be reduced to one lane for roadside sign installation work. This closure will be in place until Thursday at 6 a.m.  

Thursday, Oct. 3 

  • Beginning at 8 p.m., the I-265 northbound to I-71 southbound ramp (Exit 35B) will be closed for bridge maintenance work. This closure will be in place until Friday at 6 a.m. 

Friday, Oct. 4 

  • Beginning at 8 p.m., I-265 northbound will be reduced to one lane south of I-64 to Shelbyville Road for permanent barrier wall installation work. This closure will be in place until Monday morning at 6 a.m.  

Work may be adjusted due to weather or other unforeseen events. Drivers should use caution when traveling through active work zones. 

I-Move Traffic Alert: Lane and Ramp Closures on I-265 Starting Tonight

Multiple lane and ramp closures will be in place on I-265 starting tonight, Monday, Sept. 23. This work is part of the I-Move Kentucky project. 

Monday, Sept. 23 New Closures 

  • Beginning at 8 p.m., I-265 northbound from I-64 to Shelbyville Road will be reduced to one lane for striping work. This closure will be in place until Tuesday at 6 a.m. 
  • I-265 northbound and I-265 southbound will be reduced to one lane in various locations between I-64 and I-71 starting Tuesday, Sept. 24 through Friday, Sept. 27 from 8 p.m. to 6 a.m. each morning. Crews will be installing rumble strips. 

Reminders 

  • Beginning Tuesday at 7 p.m., the I-64 westbound to I-265 southbound ramp will be closed for added surface paving treatment. This closure will be in place until Wednesday at 6 a.m.  
  • Various locations along I-265 northbound and I-265 southbound from I-64 to Brownsboro Road will experience lane reductions starting Monday, Sept. 23 through Friday, Sept. 27 from 8 p.m. until 6 a.m. each morning for striping and pavement marker installation.  

Work may be adjusted due to weather or other unforeseen events. Drivers should use caution when traveling through active work zones. 

I-Move Traffic Alert: Lane and Ramp Closures on I-64 and I-265 Starting Tonight

Multiple lane and ramp closures will be in place on I-64 and I-265 starting tonight, Friday, Sept. 20. This work is part of the I-Move Kentucky project.  

Friday, Sept. 20 

  • Beginning at 8 p.m., I-265 northbound from Pope Lick Road (Mile Marker 24.8) to just past the I-64 bridge (Mile Marker 25.8) will be reduced to one lane for final surfacing work. This closure will be in place until Monday morning at 6 a.m. 
  • At 8 p.m., the I-265 northbound ramp to I-64 eastbound will be closed for final surfacing work. This closure will be in place until Saturday at midnight. 

The detour will be to take I-265 northbound to Shelbyville Road (Exit 27) or Old Henry Road (Exit 29) and then take either the I-265 southbound or I-64 eastbound ramp.  

  • At 8 p.m., the I-265 northbound ramp to I-64 westbound will be closed for final surfacing work. This closure is in place until Saturday at midnight. 

The detour will be to take I-265 northbound to Shelbyville Road (Exit 27) or Old Henry Road (Exit 29) and then take I-265 southbound to the I-64 westbound ramp.  

  • At 8 p.m., the I-64 westbound ramp to I-265 northbound will be closed for final surfacing work. This closure is in place until Monday morning at 6 a.m. 

The detour will be to take I-64 westbound to Blankenbaker Parkway and then take I-64 eastbound to the I-265 southbound ramp to Taylorsville Road (Exit 23), then take the I-265 northbound ramp.  

  • At 8 p.m., the I-64 eastbound to I-265 northbound ramp will be closed for final surfacing work. This closure will be in place until Saturday at midnight. 

The detour will be to take the I-64 eastbound ramp to I-265 southbound to the Taylorsville Road exit (Exit 23), then take the ramp to I-265 northbound.  

 

Monday, Sept. 23 

  • Beginning at 7 p.m., the I-64 westbound to I-265 southbound ramp will be closed for added surface paving treatment. This closure will be in place until Tuesday at 6 a.m.  
  • Various locations along I-265 northbound and I-265 southbound from I-64 to Brownsboro Road will experience lane reductions starting Monday, Sept. 23 through Friday, Sept. 27 from 8 p.m. until 6 a.m. each morning for striping and pavement marker installation.  

Work may be adjusted due to weather or other unforeseen events. Drivers should use caution when traveling through active work zones. 

I-Move Traffic Alert: Lane and Ramp Closures on I-71 and I-265 Starting Tomorrow  

Lane and ramp closures will be in place on I-71 and I-265 starting tomorrow, Friday, Sept. 13. This work is part of the I-Move Kentucky project.

Friday, Sept. 13 

Beginning at 8 p.m., the ramp from KY 329 to I-71 southbound will be closed. Crews will be performing pavement work on the ramp. This closure is in place until Monday morning at 6 a.m.

Also, at 8 p.m., I-71 southbound will be reduced to one lane from KY 329 (Mile Marker 15) to just past Moser Farm Road Bridge (Mile Marker 11).

Monday, Sept. 16 

Monday, Sept. 16 through Friday, Sept. 20 from 8 p.m. until 6 a.m. daily, I-265 southbound and I-265 northbound will be reduced to one lane in various locations throughout the corridor from Shelbyville Road to Brownsboro Road. These lane reductions will be in place for pavement marker installation.

Work may be adjusted due to weather or other unforeseen events. Drivers should use caution when traveling through active work zones.

I-Move Week Ahead: Lane and Ramp Closures on I-71 and I-265 Starting Tonight

*Additional closures in bold

Lane and ramp closures will be in place on I-71 and I-265 starting tonight, Friday, Aug. 30. This work is part of the I-Move Kentucky project.  

Fri., Aug. 30 

  • Beginning at 10 p.m., the ramps from I-265 northbound to I-71 southbound (Exit 35B), I-71 southbound to I-265 southbound (Exit 9A), and I-265 southbound to I-71 northbound (Exit 35A) will be closed. Crews will be performing bridge maintenance work. This closure will be in place until 6 a.m. Saturday morning.  
  • At 10 p.m., I-71 South and I-71 North will be reduced to one lane at the Gene Snyder. Crews will be performing bridge maintenance work. This closure will be in place until 6 a.m. Saturday morning.  

Tues., Sept. 3 

  • Beginning at 8 p.m., I-265 northbound at I-64 will have a full closure. The detour for this closure will be to take the I-265 northbound ramp to I-64 westbound (Exit 25B), turn around at Blankenbaker Parkway then take I-64 eastbound to I-265 northbound (Exit 19). Crews will be working on the future I-64 westbound to I-265 northbound ramp.  
  • Beginning at 8 p.m., I-265 northbound will be reduced to one lane from I-71 to KY 42. Crews will be performing pavement installation. This closure will be in place until 6 a.m. Wednesday morning. 

Wed., Sept. 4 

  • Beginning at 9 a.m., there will be intermittent one lane rolling road closures on I-71 northbound from the rest area to KY 329. This closure will be in place until 1 p.m. 
  • Beginning at 8 p.m., I-265 northbound will be reduced to one lane from I-71 to KY 42. Crews will be performing pavement installation. This closure will be in place until 6 a.m. Thursday morning.  
  • At 8 p.m., I-265 southbound from Shelbyville Road to I-64 will be reduced to one lane for overhead sign work. This closure will be in place until 6 a.m. Thursday.  

Work may be adjusted due to weather or other unforeseen events. Drivers should use caution when traveling through active work zones. 

I-Move Traffic Alert: Additional Lane and Ramp Closures on I-71, I-64 and I-265 Starting Tonight

Additional lane and ramp closures will be in place on I-71, I-64 and I-265 starting Monday, Aug. 26. This work is part of the I-Move Kentucky project.  

Mon., Aug. 26 

  • Beginning at 8 p.m., I-71 southbound will be reduced to one lane from Moser Farm Road until Brownsboro Road. Crews will be performing electrical work in the area. This closure will be in place until 6 a.m. Tuesday morning. 

Tues., Aug. 27 

  • Beginning at 8 p.m., I-71 southbound will be reduced to one lane from Moser Farm Road until Brownsboro Road. Crews will be performing electrical work in the area. This closure will be in place until 6 a.m. Wednesday morning. 
  • Beginning at 8 p.m., I-265 northbound lanes between Westport Road (Exit 32) and Brownsboro Road (Exit 34) will be reduced to one lane. This closure will be in place until 6 a.m. Wednesday morning. 

Wed., Aug. 28 

  • Beginning at 6 a.m., I-265 northbound traffic between Westport Road (Exit 32) and Brownsboro Road (Exit 34) will be shifted to the left side of the road. This will be a long-term shift. 
  • Beginning at 8 p.m., the ramp from I-265 South to I-64 West (Exit 25B) will be closed. This closure will be in place until 6 a.m. Thursday morning.  
  • Beginning at 8 p.m., I-265 southbound from Shelbyville Road to I-64 will be reduced to one lane. This closure will be in place until 6 a.m. Thursday morning.  
  • Beginning at 8 p.m., I-265 northbound from I-71 to US 42, will be reduced to one lane. This closure will be in place until 6 a.m. Thursday. The same closure will be in place Thursday night.  

Thurs., Aug. 29 

  • Beginning at 8 p.m., I-64 eastbound will be reduced to one lane from Blankenbaker Parkway until I-265. Crews will be performing electrical work in the area. This closure will be in place until 6 a.m. Friday morning.  
  • Beginning at 6 a.m., the current split of traffic on I-265 South at Shelbyville Road will be eliminated. All lanes of traffic will now be on the right side of the permanent barrier wall. A right-side lane closure from the Shelbyville Road ramp onto I-265 southbound will stay in place. 
  • Beginning at 8 p.m., I-265 northbound from I-71 to US 42, will be reduced to one lane. This closure will be in place until 6 a.m. Friday morning.  

Work may be adjusted due to weather or other unforeseen events. Drivers should use caution when traveling through active work zones. 

 

About I-Move Kentucky 

The I-Move Kentucky project includes improvements to four major sections of I-265, I-71 and I-64 through a heavily traveled corridor in Jefferson and Oldham counties. Work on the I-Move project is scheduled to continue until fall of 2024. 

I-Move Week Ahead: Multiple Lane and Ramp Closures on I-71 and I-265 Starting Tonight

Multiple lane and ramp closures will be in place on I-71 and I-265 starting Friday, Aug. 23. This work is part of the I-Move Kentucky project.

Friday, Aug. 23 

  • Beginning at 8 p.m., the exit from I-71 northbound to KY 329 will be closed for paving. This closure will be in place until noon on Saturday.  
  • Beginning at 8 p.m., I-71 northbound from the rest area to the KY 329 overpass will be reduced to one lane. Crews will be working on the surface pavement.  This closure will be in place until 6 a.m. Monday morning. 
  • Beginning at 8 p.m., I-265 northbound from Brownsboro Road to I-71 will be reduced to one lane. Crews will be performing concrete paving. This closure will be in place until 6 a.m. Monday morning.  

Sunday, Aug. 25 

  • Beginning at 3 p.m., I-265 North at Shelbyville Road (Exit 27) will be reduced to one lane. Crews will be performing highway lighting maintenance. This closure will be in place until 6 p.m. Sunday.  
  • Beginning at 3 p.m., ramps from I-265 North to I-71 South, I-71 South to I-265 South, and I-265 South to I-71 North will be closed. Crews will be performing bridge maintenance work. This closure will be in place until 6 a.m. Monday morning.  
  • Beginning at 3 p.m., I-71 southbound and I-71 northbound will be reduced to one lane at the Gene Snyder. Crews will be performing bridge maintenance work. This closure will be in place until 6 a.m. Monday morning. 

Tuesday, Aug. 27 

  • Beginning at 8 p.m., I-265 northbound lanes between Westport Road (Exit 32) and Brownsboro Road (Exit 34) will be reduced to one lane. This closure will be in place until 6 a.m. Wednesday morning. 

Wednesday, Aug. 28 

  • Beginning at 6 a.m., I-265 northbound traffic between Westport Road (Exit 32) and Brownsboro Road (Exit 34) will be shifted to the left side of the road. This will be a long-term shift. 
  • Beginning at 8 p.m., the ramp from I-265 South to I-64 West (Exit 25B) will be closed. This closure will be in place until 6 a.m. Thursday morning.  
  • Beginning at 8 p.m., I-265 southbound from Shelbyville Road to I-64 will be reduced to one lane. This closure will be in place until 6 a.m. Thursday morning.  
  • Beginning at 8 p.m., I-265 northbound from I-71 to US 42, will be reduced to one lane. This closure will be in place until 6 a.m. Thursday. The same closure will be in place Thursday night.  

Thursday, Aug. 29 

  • Beginning at 6 a.m., the current split of traffic on I-265 South at Shelbyville Road will be eliminated. All lanes of traffic will now be on the right side of the permanent barrier wall. A right-side lane closure from the Shelbyville Road ramp onto I-265 southbound will stay in place. 
  • Beginning at 8 p.m., I-265 northbound from I-71 to US 42, will be reduced to one lane. This closure will be in place until 6 a.m. Friday morning.  

Work may be adjusted due to weather or other unforeseen events. Drivers should use caution when traveling through active work zones. 

I-Move Traffic Alert: Lane Closures on I-71 North and I-265 North Starting Friday

Lane closures on I-71 North and I-265 North will be in place starting Friday, Aug. 23. This work is part of the I-Move Kentucky project.  

Beginning Friday at 8 p.m., I-71 northbound from the rest area to the KY 329 overpass will be reduced to one lane. Crews will be working on surface pavement of that section of the roadway. This closure will be in place until 6 a.m. Monday morning. 

Also, beginning Friday at 8 p.m., I-265 northbound from Brownsboro Road to I-71 will be reduced to one lane. Crews will be performing concrete paving. This closure will be in place until 6 a.m. Monday morning.  

Work may be adjusted due to weather or other unforeseen events. Drivers should use caution when traveling through active work zones. 

I-Move Traffic Alert: Lane Closures on Shelbyville Road Under I-265 Starting Monday

Lane closures on Shelbyville Road under Interstate I-265 will be in place on Monday, Aug. 19. This work is part of the I-Move Kentucky project.  

Beginning Monday at 9 a.m., Shelbyville Road under I-265 will be reduced to one lane in both directions. Crews will be performing roadway lighting upgrades. This closure will be in place until 3 p.m. on Monday.  

Work may be adjusted due to weather or other unforeseen events. Drivers should use caution when traveling through active work zones.