Weekend Report: Bridge work requires I-265 lane closure

Traffic impacted on I-265 northbound and southbound near I-64 interchange

The Kentucky Transportation Cabinet continues to make progress on the I-Move Kentucky project as crews work in several areas of I-71, I-64 and I-265. Bridge work over I-64 will require a lane closure tonight and tomorrow.

Starting tonight (Friday) at 8 p.m. until Saturday at 5 p.m., traffic will reduced by one lane on I-265 northbound and southbound to accommodate bridge work at the I-64/I-265 interchange. The closure will begin just before the interchange at mile point 25.4. It will allow construction crews to prep and pour the middle pier of the bridge over I-64.

An ongoing lane closure is also in place on I-64 westbound near the interchange. Temporary rest area closures on I-71 northbound also continue this weekend while blasting work is under way daily.

Work schedules may be adjusted due to weather or other unforeseen delays. Drivers should be cautious when traveling through active construction areas. Signage and flaggers will be in place to alert drivers of lane closures and construction zones.

Other I-Move Kentucky Work Areas

I-71/I-265 interchange – Work continues on new bridges, access ramps and along I-71 at mile point 9.1. The new collector-distributor lane recently opened to improve safety for vehicles entering and exiting the roadway. No traffic impacts are planned this weekend.

I-265/I-64 interchange – Traffic will be reduced by one lane on I-64 westbound near the I-265 interchange while bridge work is performed overhead for several weeks.The closure will begin after the I-64 westbound to I-265 northbound ramp shifting the acceleration lane for traffic merging onto the mainline roadway to the left at mile point 19. This is in addition to the traffic impact listed above.

I-71 – Blasting work on I-71 northbound and southbound is under way and continues daily. This will require rolling lane closures and short-term road closures daily, including some weekends, between noon and 3 p.m. while blasting is completed near mile point 11.8. Closures are necessary during excavation work for the safety of construction crews and the public.

Excavation work near the I-71 northbound rest area will require temporary closures of the rest stop daily. This closure will ensure the safety of the public and construction crews while evacuation work is conducted nearby. Crews will close the entrance to the rest area at 1 p.m. and check for any remaining vehicles at 2 p.m. before conducting blasting work between 2:30 and 3 p.m. daily. Barricades will be removed, and the rest area will be reopened when deemed safe by construction crews following blasting.

Preparation work in this area is ongoing to allow for widening of the corridor and construction of a new Brownsboro Road (KY 1694) bridge over I-71. This work zone is located between mile point 10.3 and mile point 9.1 of I-71 southbound. No traffic impacts are expected this week. Crews continue to work to extend a culvert that will allow for the widening of I-71. No traffic impacts are expected as work continues between mile point 14.5 and mile point 13.5 of I-71 southbound.

About I-Move Kentucky

The I-Move Kentucky project includes improvements to four major sections of I-265, I-71 and I-64 through a heavily traveled corridor in Jefferson and Oldham counties. Work on the I-Move project is scheduled to be completed by the end of 2023.

Stay informed through the following channels:

Website www.I-MoveKY.com
Facebook facebook.com/IMoveKY/
Twitter twitter.com/IMoveKY
Email alerts/newsletters – Signup at www.I-MoveKY.com
Mobile alerts – Text “IMOVEKY” to 74121

Week Ahead: I-71 rest area closure and I-64 lane closure start this week

Traffic will be impacted for several days in Jefferson and Oldham counties

The Kentucky Transportation Cabinet continues to make progress on the I-Move Kentucky project as crews work in several areas of I-71, I-64 and I-265. Excavation work along I-71 and bridge work over I-64 will require ongoing closures starting this week.

Starting tonight (Tuesday) at 8 p.m. and continuing for several weeks, traffic will be reduced to two lanes on I-64 eastbound near the I-265 interchange at mile point 19 for work on the I-265 bridge pier overhead. The left lane will be closed from the I-265 southbound ramp to past the I-265 bridge.

On Wednesday from 9 a.m. until 3 p.m., traffic will be reduced to one lane on I-265 southbound to perform pothole repairs. The lane closure will begin near the I-64 westbound ramp and end at the I-64 bridge at mile point 25.4.

On Thursday from 1 p.m. to approx. 3 p.m. and continuing daily at the same time, the rest area on I-71 northbound at mile point 13 will be temporarily closed. This closure will ensure the safety of the public and construction crews while evacuation work is conducted nearby. Crews will close the entrance to the rest area at 1 p.m. and check for any remaining vehicles at 2 p.m. before conducting blasting work between 2:30 and 3 p.m. daily. Barricades will be removed, and the rest area will be reopened when deemed safe by construction crews following blasting.

On Thursday from 9 a.m. to 3 p.m., traffic will be reduced to one lane on I-71 southbound to mobilize equipment for the installation of a sound wall. The lane closure will begin north of Moser Farm Road near mile point 11.8 and end south of Brownsboro Road at mile point 10.3.

Work schedules may be adjusted due to weather or other unforeseen delays. Drivers should be cautious when traveling through active construction areas. Signage and flaggers will be in place to alert drivers of lane closures and construction zones.

Other I-Move Kentucky Work Areas

I-71/I-265 interchange – Work continues on new bridges, access ramps and along I-71 at mile point 9.1. The new collector-distributor lane recently opened to improve safety for vehicles entering and exiting the roadway. No traffic impacts are planned this week.

I-71 northbound to Moser Farm Road – Blasting work on I-71 northbound and southbound at Moser Farm Road is under way and continues daily. This will require rolling lane closures and short-term road closures daily, including some weekends, between noon and 3 p.m. while blasting is completed near mile point 11.8. Closures are necessary during excavation work for the safety of construction crews and the public.

I-71 southbound between Brownsboro Road bridge and I-265 bridge – Preparation work in this area is ongoing to allow for widening of the corridor and construction of a new Brownsboro Road (KY 1694) bridge over I-71. This work zone is located between mile point 10.3 and mile point 9.1 of I-71 southbound. No traffic impacts are expected this week.

I-71 southbound between Highway 329 and the rest area – Crews continue to work to extend a culvert that will allow for the widening of I-71. No traffic impacts are expected as work continues between mile point 14.5 and mile point 13.5 of I-71 southbound.

I-265 between Taylorsville Road and I-64 – Interior lanes of I-265 between Taylorsville Road and I-64 were recently paved. No traffic impacts are anticipated as crews perform this work and continue drainage and lane widening work in the median between mile point 25.4 and mile point 23.1.

About I-Move Kentucky

The I-Move Kentucky project includes improvements to four major sections of I-265, I-71 and I-64 through a heavily traveled corridor in Jefferson and Oldham counties. Work on the I-Move project is scheduled to be completed by the end of 2023.

Stay informed through the following channels:

Website www.I-MoveKY.com
Facebook facebook.com/IMoveKY/
Twitter twitter.com/IMoveKY
Email alerts/newsletters – Signup at www.I-MoveKY.com
Mobile alerts – Text “IMOVEKY” to 74121

Week Ahead: Lane closures planned Sunday and Monday to install barrier walls and signage

Traffic on I-265 and I-71 will be impacted next week

 The Kentucky Transportation Cabinet continues to make progress on the I-Move Kentucky project as crews work in several areas of I-71 and I-265. Crews will not be working Thursday, Dec. 24 to Saturday, Dec. 26 to observe the holiday. Work will resume Sunday to install barrier walls and new signage requiring lane closures Dec. 27 and Monday, Dec. 28.

From 8 p.m. Sunday to 6 a.m. Monday, I-71 southbound will be reduced to one lane from mile point 12 to near Chamberlain Lane near mile point 9.8. I-265 northbound will also be reduced to one lane from the I-64 eastbound exit at mile point 25.4 to Shelbyville Road at mile point 26.8. Temporary barrier walls are being installed in both areas for the safety of motorists and construction workers.

From 8 p.m. Monday to 6 a.m. Tuesday, I-71 southbound will be reduced to one lane from near Chamberlain Lane at mile point 9.8 to near the I-71/I-265 interchange at mile point 9.1. Crews will be setting signage on the new sign truss over I-71. At the same time, I-265 northbound will be reduced to one lane from the I-64 eastbound exit at mile point 25.4 to Shelbyville Road at mile point 26.8 while work to install temporary barrier walls continues. I-265 northbound will also be reduced to one lane from south of Shelbyville Road at mile point 26.8 to the I-64 overpass at mile point 25.4 to install a barrier wall.

I-Move Kentucky is nearing completion of the collector-distributor lane on I-71 southbound at I-265 interchange. Additional closures may be announced early next week related to the final traffic shift.

Work schedules may be adjusted due to weather or other unforeseen delays. Drivers should be cautious when traveling through active construction areas. Signage and flaggers will be in place to alert drivers of lane closures and construction zones.

Other I-Move Kentucky Work Areas

I-71/I-265 interchange – Work continues on new bridges, access ramps, along I-71 and the widening of the corridor to add a collector-distributor lane will improve safety for vehicles entering and exiting I-71 at mile point 9.1. See planned traffic impacts listed above.

I-71 northbound to Moser Farm Road – Blasting work on I-71 northbound and southbound at Moser Farm Road is under way and continues daily. Excavation work is needed to eventually widen this area of the I-71 corridor to a total of six lanes. Rolling lane closures and short-term road closures will take place on both northbound and southbound lanes daily, including some weekends, between noon and 3 p.m. while blasting is completed near mile point 11.8 of I-71 northbound.

I-71 southbound between Brownsboro Road bridge and I-265 bridge – Preparation work in this area is ongoing to allow for widening of the corridor and construction of a new Brownsboro Road (KY 1694) bridge over I-71. This work zone is located between mile point 10.3 and mile point 9.1 of I-71 southbound. No traffic impacts are expected this week.

I-71 southbound between Highway 329 and the rest area – Crews continue to work to extend a culvert that will allow for the widening of I-71. No traffic impacts are expected as work continues between mile point 14.5 and mile point 13.5 of I-71 southbound.

I-265 between Taylorsville Road and I-64 – Interior lanes of I-265 between Taylorsville Road and I-64 were recently paved. No traffic impacts are anticipated as crews perform this work and continue drainage and lane widening work in the median between mile point 25.4 and mile point 23.1.

I-Move Update: Closures planned for ramp repair, bridge construction Sunday and Monday

The Kentucky Transportation Cabinet continues to make progress on the I-Move Kentucky project as crews work in several areas of I-71 and I-265.

On Sunday, repairs to the ramp from I-71 southbound to I-265 southbound will require the ramp to be closed from 8 a.m. to 12 p.m. Crews will be replacing a crash cushion device to provide added safety by limiting the damage that can occur should vehicles leave the roadway.

On Monday, traffic on I-265 northbound near the I-71/I-265 interchange will be reduced to one lane from 9 a.m. to 3 p.m. Lane closures will start near Brownsboro Rd. at mile point 34.1 and end past the I-71 interchange near mile point 34.7. Construction crews will be pouring a new bridge deck for the bridge over I-71. This marks a significant milestone as I-Move Kentucky rebuilds this important interchange to improve safety and ease the flow of traffic on the roadway.

Work schedules may be adjusted due to weather or other unforeseen delays. Drivers should be cautious when traveling through active construction areas. Signage and flaggers will be in place to alert drivers of lane closures and construction zones.

Other I-Move Kentucky Work Areas

I-71/I-265 interchange – Work continues on new bridges, access ramps, along I-71 and the widening of the corridor to add a collector-distributor lane will improve safety for vehicles entering and exiting I-71 at mile point 9.1. See planned traffic impacts listed above.

I-71 northbound to Moser Farm Road – Blasting work on I-71 northbound and southbound at Moser Farm Road is under way and continues daily. Excavation work is needed to eventually widen this area of the I-71 corridor to a total of six lanes. Rolling lane closures and short-term road closures will take place on both northbound and southbound lanes daily, including some weekends, between noon and 3 p.m. while blasting is completed near mile point 11.8 of I-71 northbound.

I-71 southbound between Brownsboro Road bridge and I-265 bridge – Preparation work in this area is ongoing to allow for widening of the corridor and construction of a new Brownsboro Road (KY 1694) bridge over I-71. This work zone is located between mile point 10.3 and mile point 9.1 of I-71 southbound. No traffic impacts are expected this week.

I-71 southbound between Highway 329 and the rest area – Crews continue to work to extend a culvert that will allow for the widening of I-71. No traffic impacts are expected as work continues between mile point 14.5 and mile point 13.5 of I-71 southbound.

I-265 between Taylorsville Road and I-64 – Interior lanes of I-265 between Taylorsville Road and I-64 were recently paved. No traffic impacts are anticipated as crews perform this work and continue drainage and lane widening work in the median between mile point 25.4 and mile point 23.1.

I-Move Week Ahead: Work near I-64/I-265 interchange requires lane closure

Traffic on I-265 will be impacted Monday and Tuesday nights

The Kentucky Transportation Cabinet continues to make progress on the I-Move Kentucky project as crews work in several areas of I-71 and I-265. Milling and paving work will impact traffic this week.

Traffic on I-265 will be reduced to one lane on Monday and Tuesday evenings between 8 p.m. and 6 a.m. between Shelbyville Road at mile point 26.8 and the I-64 interchange at mile point 25.4 for milling and paving operations. Lanes will be shifted for ongoing work to improve safety and mobility by rebuilding the I-64/I-265 interchange.

Looking ahead to the weekend, paving and milling operations on a two-mile stretch of I-71 northbound will require traffic to be reduced to one lane from Saturday at 12 a.m. to Monday at 6 a.m. Lane closures will start north of Chamberlain Lane near mile marker 9.8 on I-71 northbound and end near Moser Farm Road at mile marker 11.8.

Work schedules may be adjusted due to weather or other unforeseen delays. Drivers should be cautious when traveling through active construction areas. Signage and flaggers will be in place to alert drivers of lane closures and construction zones.

Other I-Move Kentucky Work Areas

I-64/I-265 interchange – Work to rebuild the interchange listed above will impact traffic on I-265 this weekend between Shelbyville Road at mile point 26.8 and the I-64 interchange at mile point 25.4.

I-71 northbound to Moser Farm Road – Paving operations listed above will impact traffic this weekend. Also, blasting work on I-71 northbound and southbound at Moser Farm Road is under way and continues daily. Excavation work is needed to eventually widen this area of the I-71 corridor to a total of six lanes. Rolling lane closures and short-term road closures will take place on both northbound and southbound lanes daily, including some weekends, between noon and 3 p.m. while blasting is completed near mile point 11.8 of I-71 northbound.

I-71/I-265 interchange – Work on new bridges, access ramps, along I-71 and the widening of the corridor to add a collector-distributor lane will improve safety for vehicles entering and exiting I-71 at mile point 9.1. No traffic impacts are planned this weekend

I-71 southbound between Brownsboro Road bridge and I-265 bridge – Preparation work in this area is ongoing to allow for widening of the corridor and construction of a new Brownsboro Road (KY 1694) bridge over I-71. This work zone is located between mile point 10.3 and mile point 9.1 of I-71 southbound. No traffic impacts are expected this week.

I-71 southbound between Highway 329 and the rest area – Crews continue to work to extend a culvert that will allow for the widening of I-71. No traffic impacts are expected as work continues between mile point 14.5 and mile point 13.5 of I-71 southbound.

I-265 between Taylorsville Road and I-64 – Interior lanes of I-265 between Taylorsville Road and I-64 were recently paved. No traffic impacts are anticipated as crews perform this work and continue drainage and lane widening work in the median between mile point 25.4 and mile point 23.1.

KYTC selects design-build team for I-Move project

$180 million project to improve I-265, I-71 and I-64 will start this spring

LOUISVILLE, Ky. (Oct. 31, 2019) – The Kentucky Transportation Cabinet (KYTC) has selected a design-build team led by Hall Contracting and American Engineers Inc. to design and construct the I-Move Kentucky interstate project. The four-year, $180 million construction project includes improvements to I-265, I-71 and I-64 through a heavily traveled corridor in Jefferson and Oldham counties.

I-Move Kentucky is the largest single construction project in Kentucky since the Ohio River Bridges Project was completed in 2016.

Hall Contracting will deliver the major project using a design-build approach that combines what had been four, individual projects near I-265, also known as the Gene Snyder Freeway. The Hall/AEI team will begin planning and pre-construction activities this fall, and some construction will start in early 2020.

The I-Move Kentucky project will add lane capacity and upgrade major interchanges to roadways that are important to the state’s transportation system and regional economic development. Employers of tens of thousands of workers, including Kroger Co., Ford Motor Co., and UPS Inc., rely on the corridor to move products throughout the state and region.

I-Move Kentucky includes four projects outlined as statewide priorities through KYTC’s data-driven Strategic Highway Investment Formula for Tomorrow (SHIFT) initiative. SHIFT was developed by KYTC to compare capital improvement projects and prioritize transportation spending.

The I-Move projects include:

  • I-265 Widening: Ranked as the No. 1 SHIFT priority, this project will widen I-265 to the center and add a 12-foot lane of traffic in each direction, creating a total of six lanes between KY 155 (Taylorsville Road) and I-71.
  • I-71/I-265 Interchange Improvements: This project will create a collector-distributor lane on southbound I-71 to improve safety and ease ramp movements to and from I-265.
  • I-71 Widening: This project will widen I-71 and add a 12-foot lane of traffic in each direction to create a total of six lanes between I-265 and KY 329 (Crestwood/Pewee Valley exit).
  • I-64/I-265 Interchange Improvements: This project will reconstruct the I-64/I-265 interchange to improve safety and ease the flow of traffic through the interchange and includes areas on I-64 from Blankenbaker Parkway to English Station Road, and on I-265 from Pope Lick Road to the U.S. 60 interchange.

Construction timeline

Construction on the I-Move Kentucky project will begin in spring 2020. KYTC and the design-build team are developing detailed plans for the construction schedule, but no specific dates have been set to start work.

Construction will begin on the I-71/I-265 interchange improvements in early spring and be completed by the end of next year. Construction work is also expected to start in 2020 on portions of the I-71 widening. The I-265 widening and I-64/I-265 interchange improvements are expected to begin in 2021. The entire project is scheduled to be completed in late 2023.

About I-Move Kentucky

I-Move Kentucky is the state’s innovative approach to improving the safety, ease of travel and quality of life for travelers and businesses that frequently use I-265, I-71 and I-64. Using a four-projects-in-one approach, the Kentucky Transportation Cabinet is addressing some of Kentucky’s highest-priority transportation needs.

Additional updates on I-Move Kentucky will be shared on social media channels:
Facebook: facebook.com/IMoveKY
Twitter: twitter.com/imoveky

KYTC selects alternative for I-64/I-265 interchange reconstruction in Jefferson County

LOUISVILLE, Ky. (May 13, 2019) –The Kentucky Transportation Cabinet (KYTC) announces selection of an alternative for reconstruction of the interchange between Interstate 64 and Interstate 265 (Gene Snyder Freeway) in Jefferson County.  Four alternatives were presented to the public earlier this year to address operations and safety concerns at this interchange.

Based upon traffic analysis, review of crash data and public input, the KYTC project team selected a partial turbine design with a braided ramp (Alternative 3B). This design addresses some of the short traffic weaving segments at the interchange by replacing two of the existing loop ramps with longer ramps that will pass under I-265. This alternate can be viewed online at http://bit.ly/I64atI265 .

Another advantage of this option is “braiding” of the two entrance ramps from I-64 onto I-265 North. The result will be improved lane assignments on I-265 North where these ramps merge to reduce the traffic weave between the I-64 and U.S. 60 interchanges.

“After a comprehensive safety analysis, including future traffic projections, the recommended alternative points to a reduction in crashes,” said Matt Bullock, chief district engineer for KYTC’s District 5 office in Louisville. “This proposed design will make interchange spacing safer and more efficient by improving some of the acceleration and deceleration lengths for traffic merging between the two interstates.”

Traffic flow through the interchange will also be enhanced by the addition of lane capacity on four high volume ramps.

The selected alternate has minimal right-of-way impacts and minor utility relocation.

Reconstruction of the I-64/I-265 interchange is part of KYTC’s recently announced I-Move Kentucky project. This $180 million design-build project will improve safety and reduce congestion through a heavily traveled interstate corridor in Jefferson and Oldham counties. The work combines four priority projects into a single construction project to add lane capacity and upgrades at two, major interchanges on I-265, I-71 and I-64.

Design-build is an effective contracting approach to deliver projects faster and often at a lower cost than traditional design-bid-build projects. While the preliminary design work has been completed on these projects, the design-build process allows the contractor to propose alternate designs that operate as efficiently as the plans advertised by KYTC while still staying within the project budget.

Construction for I-Move Kentucky is scheduled to begin in 2020.

KYTC announces state’s second largest design-build project to improve I-265, I-71, I-64

Best value contracting approach reduces construction time, minimizes traffic impacts, stretches dollars

Louisville, KY (April 26, 2019) — The Kentucky Transportation Cabinet (KYTC) announced plans today for a $180 million design-build project that will improve safety and reduce congestion through a heavily traveled interstate corridor in Jefferson and Oldham counties. It will be the largest, single construction project in Kentucky since the Ohio River Bridges Project was completed in 2016.

The four-year project, called I-Move Kentucky, will add lane capacity and include upgrades at two, major interchanges on Interstates 265, I-71 and I-64. Combining the priority projects into a single construction project and using a design-build approach will allow the Cabinet to make improvements more quickly and efficiently.

“I-Move Kentucky will improve safety and mobility on three major interstates that join together in eastern Jefferson County and will allow travelers and freight to move freely through the region,” KYTC Secretary Greg Thomas said. “These were among the most important projects identified during last year’s SHIFT prioritization. By tackling them together, we’re saving Kentucky taxpayers time and money.”

KYTC developed the data-driven Strategic Highway Investment Formula for Tomorrow (SHIFT) approach to objectively compare capital improvement projects and prioritize transportation spending. Incorporating input from local transportation officials, SHIFT was used to outline transportation priorities for FY 2018-FY 2024 and serve as a guide for lawmakers to develop the state’s 2018 Highway Plan.

Four projects in one

The four projects included in I-Move Kentucky were identified as statewide priorities by SHIFT.

I-265 widening: This project was identified by SHIFT as Kentucky’s No. 1 transportation priority. KYTC will widen I-265 to the center and add one, 12-foot lane of traffic in each direction to create a total of six lanes between KY 155 (Taylorsville Road) and Interstate 71.

I-71/I-265 Interchange improvements: This project was identified by SHIFT as Kentucky’s No. 6 transportation priority. KYTC will create a collector-distributor lane on southbound I-71 to improve safety and ease ramp movements to and from I-265.

I-71 widening:  This project was identified by SHIFT as Kentucky’s No. 11 transportation priority. KYTC will widen I-71 to the center and add one, 12-foot lane of traffic in each direction to create a total of six lanes between Interstate 265 and KY 329 (Crestwood/Pewee Valley exit).

I-64/I-265 Interchange improvements: KYTC will reconstruct the I-64/I-265 interchange to improve safety and ease the flow of traffic through the interchange. The project includes areas on I-64 from Blankenbaker Parkway to English Station Road, and on I-265 from Pope Lick Road to the U.S. 60 interchange.

“Interstates drive Kentucky’s economy,” said Sen. Ernie Harris, chairman of the Senate Transportation Committee. “These needed transportation improvements will move citizens and commerce faster and safer in this bustling region of the state where hundreds of thousands of people live, work and do businesses. I’m pleased that Kentucky is able to fast-track them through the I-Move Kentucky project.”

“This is a tremendous project – not just for those of us who use these interstates daily but also for citizens throughout the region and across the state,” said Rep. Jerry T. Miller, who represents Jefferson and Oldham counties. “These interstates support tens of thousands of jobs at manufacturing, distribution and logistics businesses that rely on them to move products through this vital freight corridor.”

Design-Build Best Value approach

To complete these projects more quickly and efficiently, KYTC will utilize a design-build approach similar to the construction method used for the Ohio River Bridges Project. Last year, the legislature passed HB 385 to provide KYTC with more flexibility in using the design-build approach for maximum efficiency. The Cabinet is also utilizing design-build for two projects in northern Kentucky.

Design-build is an effective contracting approach to deliver projects faster and often at lower cost than traditional design-bid-build projects. Because the project design and construction responsibilities are handled by a single project team instead of multiple project-specific teams, design-build also allows for improved coordination to limit traffic impacts during large, multi-phase construction projects.

KYTC has notified the construction industry that it is seeking teams to compete for the opportunity to build the I-Move Kentucky project, and a team will be selected this fall. The selection will be based on the “best value” provided by teams.

In addition to the four projects identified, KYTC will provide contractors with a list of other needs in the project corridor, and will evaluate teams’ ability to address these other needs as part of this project. Examples may include widening additional areas of the interstates or additional interstate ramp improvements.

Project timeline

Following the selection of a design-build team this fall, KYTC anticipates pre-construction work would begin late in 2019 and continue into next year. This work would include conducting additional engineering analysis and plan development.

Construction is expected to begin on the I-71/I-265 interchange improvements in early spring next year and be completed by the end of 2020. The timetable for other phases of the project will be determined once a design-build team is selected.

Construction is scheduled to last through 2023.